Process
How we work.
The Three Gates
Fabrication never begins without three things.
- An approved door sample.
- Signed shop drawings.
- The deposit.
Why: it protects the schedule. A project that clears the gates doesn't stall in the shop, and a finish approved on a physical sample doesn't get argued about at install.
Lead Times
Quoted by project size. Held.
| Under $50K | 6–8 weeks |
|---|---|
| $50–100K | 8–10 weeks |
| $100K+ | 10+ weeks |
Measured from the day the third gate clears.
How We Communicate
Problems are flagged early, with a fix attached.
The GC always knows status without asking. If a slab is backordered or a site condition changes the drawings, you hear it from us first — with the revised plan, not just the problem.